Mini Minor Works

Updated: 23 Jun 2023
Templates and resources for construction contracts valued at less than $250,000 with simple terms.


The Mini Minor Works (MMW) standard form is provided to help NSW Government agencies to document and manage simple construction contracts with an estimated value of up to $250,000 or less for engagements under the General Construction Works Valued up to $1 Million Scheme (SCM0256).

Download standard form document

Download sample letters

View guidance

Refer to the Creating a Mini Minor Works tender document guide for instructions on how to use the standard form.

Refer to the Mini Minor Works clause commentary for guidance on specific clauses.

View amendments

  • Clause 5: Updated requirements for consistency with WHS legislation. Updated reference to WHS Management Systems and Auditing Guidelines. Included a requirement for incidents to be investigated and reported, if instructed.
  • Clause 6: Updated to reflect current Long Service Corporation requirements.
  • Clause 8: Included insurance requirements for sole traders.
  • Contract schedule – WHS Management Plan: Updated terminology and requirements.
  • Contract schedule – Combined Subcontractor’s Statement and Supporting Statement: Updated for consistency with GC21 and MW21 and to correct errors.
  • Generally: updated references from OHS to WHS; adopted the term ‘instructed’ for consistency with other standard forms. Updated references to agencies and NSWBuy. Corrected typos and formatting.
  • Clause 14: Amended the name of the organisation to nominate an expert if the parties are unable to agree, from ‘Australian Commercial Disputes Centre’ to ‘Australian Disputes Centre’ and added a contact number.
  • Combined Subcontractor’s Statement and Supporting Statement: Corrected reference to clause 19 in the Building and Construction Industry Security of Payment Regulation 2008.
  • Removed reference to ProcurePoint and added reference to buy.nsw website.
  • Updated NSW Procurement Service Centre email address.
  • Updated reference to the current Work Health and Safety, and Environmental management guidelines in the relevant sections.
  • Updated references to SafeWork NSW from WorkCover.
  • Removed reference to WRAPP Report and added reference to NSW EPA Construction and demolition waste toolkit.
  • Generally: Corrected reference errors and formatting inconsistencies. Revised and updated user guidance. Added footer and amended header. Included auto-fill of contract name and contract number using quick-parts feature
  • Clause T3: Updated references to NSW Government codes and guidelines. added reference to Procurement Policy Framework.
  • Clause T7: Revised guide notes to always require a completed WHS & Environmental tender schedule and refer to Minor Works contract form if additional schedules are required.
  • Clause T8: Added option for alternative tenders.
  • Clause T9: Amended clause to always require tenders via eQuote.
  • Clause T11: Amended clause to include the application of government policy to late tenders and tender negotiations and the principal's right to assess qualifications.
  • Schedule 3: Deleted guide note.
  • Clause 2.1: Updated references to NSW Government codes and guidelines. Added reference to Procurement Policy. Added obligation to support skills development.
  • Clause 2.3: Amended requirement to comply with an instruction to 3 business days.
  • Clause 2.7: added clause to allow parties to change contract terms.
  • Clause 5.2: Amended time to provide a WHS Management Plan from 3 to 5 business days before starting work.
  • Clause 6.1: Amended clause to require LSL evidence before starting work.
  • Clause 10.2: Added clause to allow the contractor to request a variation where site conditions or statutory conditions require a change to the works.
  • Clause 10.4: Amended clause so that the 15% margin includes any delay costs.
  • Clause 11.2: Added requirement or contractor to notify if it expects to be delayed.
  • Clause 11.3: Added clause to allow the contractor to request an extension of time.
  • Clause 11.4: Added clause to inform the contractor that it had no extra entitlement for delay and disruption.
  • Clause 13.1: Amended clause to only allow monthly payment claims and deleted reference to contract information item 6.
  • Clause 13.3b: Amended clause to refer to revised supporting and subcontractor statements.
  • Clause 13.6: Amended clause to allow principal to only reduce payment if no subcontractor statement is provided.
  • Clause 13.7: Amended clause to require the contractor to advise nominated account for payments and any updating of the account.
  • Clause 13.10: Amended clause to change final payment schedule to final payment summary.
  • Clause 13.11: Added clause to require the contractor to submit a final payment claim.
  • Clause 13.12: Amended clause to allow the principal to make a final payment where no payment claim is received.
  • Clause 14.2: Amended clause to remove reference to senior executives.
  • Clause 17.2: Amended clause to restrict 2% payment upon termination to only apply after 25% of the contract work has been completed.
  • Item 2: Amended text to inform the contractor that payment claims are to be served to the authorised person.
  • Item 6: Deleted item 6 dealing with options for the timing of payment claims.
  • Item W.3: Amended guide note.
  • Item W.5: Deleted duplicated reference.
  • Item W.6: Amended text for services identification actions.
  • Item W.7: Added safely to clause and replaced 'authorised person' with the 'principal'.
  • Item W6: Replace 'material' with 'substances' in the sub-heading.
  • Item W.14: Added 'unexpected' to clause dealing with hazardous substances.
  • Item W.16: Added 'unexpected' to clause dealing with instructions to deal with hazardous substances.
  • Item W.18.3: Amended text to include restoration.
  • Item W.19: Amended guide note.
  • Contract Schedule - WHS Management Plan: Amended text to suit Work Health and Safety management guidelines 6th Edition.
  • Contract Schedule - Environmental Management Plan: Amended guide note and reformatted table to reduce size.
  • Contract Schedule - Supporting Statement and Subcontractor's Statement: Replaced schedules with revised and updated schedules.

General

  • Corrections and clarifications carried out. Formatting improved for consistency.
  • Suggestions for improvements and feedback on changes are encouraged.

General Conditions of Contract

  • Clause 13.2. New clause requiring payment claims to be served on the authorised person at a nominated address added.

Works Description

  • Clause W3.4. Clauses dealing with services clarified
  • Clause W6.18.5. Decontamination of hazardous substances during demolition clarified.
  • Clause W7.19. New clause listing contract schedules added.
  • Contract Schedules. Schedules re-arranged.
  • Supporting statement and subcontractor statement. Introduction and subcontractor statement amended to provide consistency with MW21 & GC21 documents.

General

  • Corrections and clarifications carried out.
  • Suggestions for improvements and feedback on changes are encouraged.

Tender Schedules

  • Signature blocks reinstated after inadvertent deletion

General

  • Corrections, formatting and clarifications carried out.
  • Suggestions for improvements and feedback on changes are encouraged.

General Conditions

  • Clause 6.1. Threshold for long service levy increased from $25,000 to $250,000 (including GST) with application from 1 January 2023.
  • Clause 8.6. Insurance term 'deductibles' replaced by 'all excesses and any deductibles' for consistency with other Contract Forms and construction works insurance policies.